The CY 2022 third quarter RPMES report consolidates the status reports of 151 projects submitted by implementing entities and state universities and colleges (SUCS). The physical and financial status reports of these projects are consolidated in RPMES Form No. 5.
Of the 151 projects, seven were found to have implementation problems or delayed with negative slippage of more than 10 percent. Among the issues cited in the reports are: (1) unavailability of construction materials due to suspension of quarry activities by the provincial government; (2) delay in delivery of construction materials; and (3) unworkable weather condition. These projects are presented in RPMES Form No. 6.